OEE calculator
Calculate Overall Equipment Effectiveness for a machine or line in under a minute. Enter one shift's numbers and see availability, performance, quality and how much capacity you are losing.
How OEE is calculated
OEE (Overall Equipment Effectiveness) multiplies three ratios: OEE = Availability × Performance × Quality. A score of 100 % means the machine made only good parts, as fast as possible, with no stops.
Availability = run time ÷ planned production time. Run time is planned production time minus downtime (breakdowns, changeovers, waiting for material).
Performance = (ideal cycle time × total count) ÷ run time. It shows how close the machine ran to its ideal speed, including short stops and slow cycles.
Quality = good count ÷ total count. Only parts that are right the first time count as good; scrap and rework do not.
Worked example
A shift has 420 minutes of planned production time and 47 minutes of downtime, so run time is 373 minutes. Availability is 373 ÷ 420 = 88.8 %.
The ideal cycle time is 1.0 second and the line made 19,271 parts. Performance is 19,271 s ÷ 22,380 s (373 minutes) = 86.1 %.
18,848 of those parts were good. Quality is 18,848 ÷ 19,271 = 97.8 %. OEE is 88.8 % × 86.1 % × 97.8 % = 74.8 %.
What is a good OEE score?
85 % is often quoted as world-class for discrete manufacturing. Many plants that start measuring find themselves between 40 % and 60 %. The trend on your own lines matters more than any benchmark: compare the same line shift by shift and look at which of the three factors pulls OEE down.
From a one-off calculation to live OEE
A calculator gives you one snapshot, and spreadsheets go stale. In P4, Production Control tracks OEE on one live data model shared with maintenance, quality and logistics, and Factory Cockpit shows OEE, output and energy per machine in real time, read from equipment over OPC UA.